Skip to content
The Release
Briefing

The End of Retentions: A Three Year Clock That Has Not Started

October 2026|9 min|6 parts
Key Takeaways
  1. KT.01The ban is a clock, not a switch. The Bill creates a two year transition period, after which new retention clauses are void, and a separate last retention day three years from commencement, after which clauses agreed or varied during the transition become ineffective and the retained cash falls due. None of it has started, because no commencement date has been appointed.
  2. KT.02The enforcement provision is the one to read. A retention withheld after the transition period without complying with section 111 becomes a retention debt carrying a fixed sum of the higher of £40 or 50 per cent of it, on top of statutory interest, and the implied term cannot be excluded.
  3. KT.03That fixed sum reaches contracts already signed. Unlike the payment terms provisions, which do not affect pre-existing contracts, the retention debt provision applies expressly to construction contracts entered into before the transition period began.

Retentions have survived every reform proposal put to Parliament for thirty years. The Commercial Payments Bill will end them, and the trade press has reported it as an event: retentions banned. The Bill does not do that. Read against the clauses rather than the headline, it sets three clocks running from a commencement date that has not yet been appointed, bans nothing on the day it is passed, leaves a category of existing retention clauses untouched, and then does something the reporting has largely missed. It attaches a fixed sum of 50 per cent to any retention withheld without a compliant payment notice, and it applies that sum to contracts signed long before the Bill existed. For anyone running a final account book, the question is not whether retentions are ending. It is which of the three clocks a given contract sits on.

PT.01

Where the Bill has actually got to

The Commercial Payments Bill [HL] is a government Bill of session 2026-27. It originated in the House of Lords on 19 May 2026, following a commitment in the 2026 King's Speech, and had an unopposed second reading on 9 June 2026. Committee stage was taken on 21 July 2026, when 105 amendments were tabled and 30 government amendments were agreed without division. Report stage was taken on 15 September 2026, and third reading is scheduled for 20 October 2026.¹

It has not yet been to the Commons. Every Commons stage, consideration of any Lords amendments and Royal Assent remain ahead of it, and the operative provisions then require commencement regulations. The version to read is HL Bill 55, as amended on Report, published on 15 September 2026. This matters for more than pedantry: report stage inserted a new clause, which moved every later clause number up by one. The retentions provisions were clauses 11 to 17 in the committee print and are clauses 12 to 18 in the current one.²

The new clause is itself worth noting. Throughout second reading and committee, peers pressed the government to go below the 60 day maximum, with support for 45 days and amendments seeking 30. The government's answer on report was a power rather than a number. New section 2F permits the Secretary of State to substitute the day counts by regulations, but only downwards: no higher than 30 for public authorities, no higher than 60 for everyone else. It also requires the Secretary of State to consult on whether to use that power within five years of the payment terms provisions coming into force.³

PT.02

Three clocks, not one switch

Clauses 12 to 18 insert new sections 113A to 113F into Part 2 of the Housing Grants, Construction and Regeneration Act 1996, immediately after section 113. Section 113A does no operative work: it defines the practice, being the deduction or retention by one party of sums equating to a percentage of the amount payable, of an interim payment or of the contract total, until a condition for release is met. The definition expressly includes conditions turning on completion of obligations, on specified conditions, and on the expiry of a defects period.⁴

The operative provisions then run on two periods, both measured from the day sections 12 and 13 commence. The first is the transition period, two years long. The second runs to the last retention day, which is the last day of three years from the same start. Sections 14, 15 and 16 do not commence with the rest: clause 32(3) brings them into force on the day after the end of the two year transition period.⁵

3 years
From commencement to the last retention day

Two years of transition, during which retention clauses may still be agreed and operated, then a void rule for anything agreed afterwards, and a further year before clauses agreed or varied during the transition become ineffective and retained cash falls due. The clock cannot start until commencement regulations are made, and none have been.

What each provision does, and when
  • 01Section 113B, ineffective retention clauses: applies to a retention clause agreed during the transition period, including in a contract entered into before it, and to a pre-existing clause varied during that period. On and after the day after the last retention day, such a clause is ineffective, as is any term providing for the treatment, release mechanism or timing of sums retained under it.
  • 02Section 113C, ban on retention clauses: applies to a retention clause agreed after the end of the transition period. Such a clause is void, as is any term providing for the treatment of sums retained under it.
  • 03Section 113D, ban on variations: the parties may not, after the transition period, agree a variation of a pre-existing retention clause or related term, and any purported variation is void, unless the variation is more favourable to the payee.
  • 04Section 113E, unauthorised retentions: the fixed sum, dealt with below, which applies to retention debts arising after the end of the transition period.
  • 05Section 113F: a power for the Secretary of State to amend the definitions in sections 113A, 113B(1) and 113C(1) by affirmative instrument, after consultation and with the consent of the Scottish and Welsh Ministers where required. This is the anti-circumvention power, and it is aimed squarely at re-labelling.

Set against each other, those provisions leave a gap that is easy to miss and commercially material. Section 113B reaches clauses agreed during the transition period and pre-existing clauses varied during it. Section 113C reaches clauses agreed after it. A retention clause in a contract entered into before commencement, and never varied during the transition period, is caught by neither. Its retention regime survives the ban as a matter of contract.⁶

The reform is not self-executing. What it changes on any given contract depends on when the clause was agreed, and on whether anyone has touched it since.

PT.03

The provision to read twice

Section 113E is where the Bill acquires teeth, and it is the provision the commentary has almost entirely passed over. It creates a new concept, the retention debt. A retention debt arises if, or to the extent that, the requirement in section 111(1) applies to a sum and is not complied with, and the sum is deducted or retained as a retention within section 113A(1). In other words, it engages where a notified sum is withheld by way of retention without a valid pay less notice.⁷

Where a retention debt arises after the end of the transition period, it is an implied term of the construction contract that the party owed the debt may recover a fixed sum of the higher of £40 or 50 per cent of the retention debt. A contract term is void so far as it purports to exclude or vary that implied term. The fixed sum is in addition to statutory interest and to any section 5A compensation, and the court may remit it in whole or part if the interests of justice require.⁷

50%
Fixed sum on an unauthorised retention

Half the retention debt again, on top of the debt and on top of statutory interest, currently 8 per cent above the Bank of England base rate. It cannot be contracted out of, and it applies to construction contracts entered into before the transition period began as well as those entered into after it.

Three features of that provision deserve attention from anyone who drafts or administers payment notices. First, it is not a penalty for retaining money; it is a penalty for retaining money without the notice the Act already requires. The trigger is non-compliance with section 111(1), which has been the law since 2011. Second, it is not capped, because 50 per cent of a large retention is a large number, and the only relief is the court's discretion to remit. Third, and least remarked, subsection (7) applies the implied term to construction contracts entered into before the transition period began or during it, as well as after. The fixed sum therefore reaches back into the existing contract book in a way the rest of Chapter 2 does not.⁷

That is a deliberate contrast. Clause 11 provides that the amendments made by clauses 1 to 9 and Schedule 1, which include the maximum payment terms, do not affect contracts entered into before the relevant provision commences. Chapter 2 on retentions carries no equivalent carve-out, and section 113E states the opposite in terms. Payment terms reform is prospective. Retentions enforcement is not.⁸

PT.04

What happens to the money already held

Section 113B does not simply switch off the clause and leave the cash where it sits. Any sum deducted or retained during the transition period in reliance on a clause caught by section 113B, and unpaid at the end of the last retention day, becomes a transitional retained sum, and the Act's payment machinery is then applied to it as though it were any other payment under the contract. The payment notice provisions, section 110B and section 111 all apply.⁹

The dates are fixed by the section rather than by the contract. The payment due date is 30 days from the day after the last retention day, or any earlier date the parties agree in writing. The final date for payment is 30 days after the payment due date where the payer is a public authority, and 60 days where it is not, again subject to any earlier agreed date.⁹

The consequence is that every payer holding retentions on affected contracts will face, on a single date, a payment cycle on the whole of that book, governed by the notice regime. A payer that wishes to withhold any part of a transitional retained sum will have to serve a compliant pay less notice to do it, and a failure to do so is precisely the circumstance in which section 113E attaches its fixed sum. The reform therefore ends by routing the entire retention book through the notified sum machinery, which is the part of the Construction Act that decides disputes on documents rather than merits.

Statute is about to convert a contractual entitlement into a payment cycle, and payment cycles are won and lost on notices.

PT.05

Sixty days, thirty for the public sector, and the settlement trap

The payment terms half of the Bill is more straightforward but contains one provision that should change drafting practice immediately on commencement. New section 2D of the 1998 Act, which the Bill renames the Commercial Payments and Interest on Late Payment Act 1998, requires the final date for payment of a relevant construction payment to fall within a permitted period: 30 days from the day after the payment due date where the purchaser is a public authority, and 60 days where it is not. A term purporting to provide otherwise is void, and the relevant Scheme provision applies instead as an implied term.¹⁰

Subsection (8) is the provision to note. A term of any other contract binding the parties, expressly including a contract settling a dispute under the main contract and a contract by which the supplier waives its right to be paid in accordance with the main contract, is void so far as it purports to vary or override the final date for payment so that it falls outside the permitted period. Settlement agreements and side letters that extend payment dates will not do the work they were drafted to do.¹⁰

Two further points of detail. The Bill amends section 110B so that the payee's default notice cannot operate to postpone the final date for payment beyond the permitted 30 or 60 day period, closing an interaction that would otherwise have undone the cap. And the separate fixed sum for raising a dispute late, in new section 11A, which the trade coverage has repeatedly described as a construction measure, expressly does not apply to construction contracts. Construction has its own fixed sum, in section 113E, on a different trigger and at a very different level.¹¹

PT.06

What the statute cannot fix

The case for the ban was never really about defects. The government's position, put by the minister after second reading, is that retentions are neither an effective means of preventing defects nor of remediating significant problems. The consultation that preceded the Bill ran from 31 July 2025 to 23 October 2025 and drew 867 responses, and the response records support for a transitional period of 12 to 24 months and a commitment to consult further before a final decision on implementation timing. That commitment is the reason the clock in the Bill has not started.¹²

The case for the ban is about what retentions are when the payer fails. The administrators of the eight ISG companies, which entered administration on 20 September 2024, state the position plainly on their own creditor page: unsecured creditor claims may include unpaid invoices, work in progress not yet invoiced or certified, retentions or any other contractual claims, and no payments are expected to be made to unsecured creditors. Recoveries of around £38.5m were reported in April 2026 against unsecured claims reported at about £885m.¹³

Nothing in the Bill changes that for money already retained. The ban operates prospectively on clauses, and the transitional machinery in section 113B converts retained cash into a payment obligation only if the payer is still solvent when the last retention day arrives. Until then, and for the whole of the transition period, the protections available are the ones that have always been available and are contractual rather than statutory.

What can be done before the clock starts
  • 01Audit the retention book by contract date and by whether the retention clause has been varied. The three categories in Chapter 2 turn on exactly that, and a variation agreed during the transition period will pull a pre-existing clause into section 113B.
  • 02Treat any variation of a retention clause as a decision with statutory consequences from commencement onwards, not as routine contract administration.
  • 03Review standing settlement and waiver templates against new section 2D(8), which voids extended payment dates agreed in a settlement of the very dispute the settlement resolves.
  • 04Secure the retention rather than relying on the covenant: project bank accounts, retention bonds, parent company guarantees and escrow all remain available and all address the insolvency exposure that the ban addresses only prospectively.
  • 05Fix the notice discipline now. Section 113E does not create a new obligation; it attaches a 50 per cent fixed sum to a failure to comply with a notice obligation that has existed since 2011.
The Meritus View

The reporting of this Bill has treated the retentions ban as a date in the future and therefore as something to be monitored rather than acted on. The clause-level reading gives a different instruction. The provision with the widest reach, the fixed sum on an unauthorised retention, is triggered by a failure to serve a compliant pay less notice, applies to contracts already signed, and cannot be excluded by agreement. It does not require anyone to change their contracts. It requires them to serve notices properly, and it prices the failure at half the sum withheld.

That is the same instruction the sequencing cases give, arrived at from the other direction. Whether a party ends up holding money or repaying it is decided by documents produced in days by people carrying out a monthly routine. This Bill takes that routine and attaches a statutory multiplier to getting it wrong. When commencement comes, the contractors who are ready will not be the ones who redrafted their subcontracts. They will be the ones who can show, contract by contract and month by month, what was notified, when, and on what basis.

Meritus Via builds that evidence base at machine speed: applications, notices, valuations, correspondence and site records ingested, reconciled and cross-referenced within hours of instruction, so that the validity of a notice, the support for a valuation and the sequence of who paid what, and when, are traceable to source within the adjudication timetable. The analysis of entitlement and the opinion remain where they belong, with senior practitioners, partner-led from first instruction through to testimony. We automate the preparation. Never the judgment.

References
  1. [1]Commercial Payments Bill [HL], session 2026-27, bill stages: first reading 19 May 2026, second reading 9 June 2026, committee stage 21 July 2026, report stage 15 September 2026, third reading scheduled for 20 October 2026 (future dates are marked provisional). Committee stage amendment figures from House of Lords Library, "Commercial Payments Bill [HL]: Progress in the Lords", LLN-2026-0049.
  2. [2]Commercial Payments Bill [HL], HL Bill 55 (as amended on Report), 15 September 2026, and HL Bill 45 (as amended in Committee), 21 July 2026. The retentions provisions are clauses 12 to 18 in HL Bill 55 and were clauses 11 to 17 in HL Bill 45.
  3. [3]HL Bill 55, clause 4, inserting section 2F (powers to shorten payment terms) into the Commercial Payments and Interest on Late Payment Act 1998: subsections (2)(a) and (4)(a) (no higher than 30 and 60 days respectively) and subsections (7) and (8) (duty to consult within five years of sections 2B and 2D coming into force). On the pressure to go below 60 days, see House of Lords Library, LLN-2026-0049, on second reading and committee stage.
  4. [4]HL Bill 55, clause 12, inserting section 113A (retention practices) into Part 2 of the Housing Grants, Construction and Regeneration Act 1996: subsection (1)(a) to (c) and subsection (2) (meaning of condition and of contract total).
  5. [5]HL Bill 55, clause 13, inserting section 113B, at subsection (10) (definitions of "the last retention day" and "the transition period"), and clause 32 (commencement), at subsection (1) (commencement by regulations) and subsection (3) (sections 14, 15 and 16 come into force the day after the end of the two year period beginning with the commencement of sections 12 and 13).
  6. [6]HL Bill 55, section 113B(2) (clauses agreed during the transition period, and pre-existing clauses varied during it), section 113C(2) and (3) (clauses agreed after the transition period are void) and section 113D (variations of pre-existing clauses after the transition period are void unless more favourable to the payee).
  7. [7]HL Bill 55, clause 16, inserting section 113E (unauthorised retentions: sum payable): subsection (1) (meaning of retention debt, by reference to section 111(1) and section 113A(1)), subsection (3) (the higher of £40 or 50 per cent), subsection (4) (void to exclude or vary), subsection (5) (remission in the interests of justice), subsection (6) (in addition to statutory interest and section 5A compensation) and subsection (7) (application to contracts entered into before or during the transition period).
  8. [8]HL Bill 55, clause 11 (no application of clauses 1 to 9 and Schedule 1 to pre-existing contracts), contrasted with Chapter 2 of Part 1, which contains no equivalent provision.
  9. [9]HL Bill 55, section 113B(3) to (9): ineffectiveness of the clause and of related release terms; the definition of a transitional retained sum; the application of section 110A(1) or the Scheme, section 110B and section 111 to such sums; the payment due date at 30 days from the day after the last retention day; and the final date for payment at 30 days (public authority payer) or 60 days (other payers) from the payment due date.
  10. [10]HL Bill 55, clause 2, inserting section 2D (payment terms: construction contracts) into the Commercial Payments and Interest on Late Payment Act 1998: subsection (3) (permitted period of 30 days for public authority purchasers and 60 days otherwise), subsection (5) (void term), subsection (6) (Scheme provision applies as an implied term) and subsections (7) and (8) (settlement agreements and waivers void so far as they push the final date outside the permitted period).
  11. [11]HL Bill 55, clause 2(4), inserting section 110B(3A) to (3D) into the Housing Grants, Construction and Regeneration Act 1996 (the payee's default notice cannot postpone the final date beyond the permitted period); and clause 8, inserting section 11A (fixed sum for late raising of disputes), which by subsection (1) applies to a contract to which the Act applies "other than a construction contract". Clause 10 renames the Late Payment of Commercial Debts (Interest) Act 1998.
  12. [12]Department for Business and Trade, letter following second reading of the Commercial Payments Bill, 24 June 2026, as summarised in House of Lords Library LLN-2026-0049 (retentions "neither an effective means of preventing defects, nor remediating significant problems"); gov.uk, "Late payments: tackling poor payment practices", consultation open 31 July 2025 to 23 October 2025 with 867 responses, and the government response "Time to pay up", which records support for a transitional period of 12 to 24 months and a commitment to consult further before a final decision on implementation. The statutory interest rate of 8 per cent above the Bank of England base rate is stated in the gov.uk Commercial Payments Bill overview factsheet; the Bill itself does not set a rate.
  13. [13]EY, ISG Administrations creditor information page: the eight ISG companies entered administration on 20 September 2024; unsecured creditor claims "may include: unpaid invoices, work in progress not yet invoiced and / or certified, retentions or any other contractual claims"; and "no payments are expected to be made to unsecured creditors of the Companies". Recoveries of approximately £38.5m against unsecured claims of approximately £885m are as reported of the joint administrators' progress report in April 2026.

The views expressed in this article are those of the author and are intended for general information only. They do not constitute legal advice and should not be relied upon as such. Specific professional advice should be sought in relation to any particular matter.

Discuss your position

Direct access to a partner. No intermediaries.

Discuss your matter
Meritus Via