Skip to content
The Ledger
Briefing

Smash-and-Grab, True Value, and the Price of a Missed Notice

June 2026|6 min|4 parts
Key Takeaways
  1. KT.01Section 111 makes the notified sum payable without deduction. Miss the payment notice and pay less notice windows and the application stands as the debt, merits notwithstanding.
  2. KT.02S&T v Grove confirmed the true-value counterweight, but it is subordinate to the immediate payment obligation. The sequencing rule is pay first, dispute second.
  3. KT.03Most smash-and-grab losses are administrative failures, not valuation disputes. Notice discipline is a system, and systems can be engineered.

The vocabulary is inelegant, but everyone in the industry understands it. A smash-and-grab adjudication seeks payment of the sum stated in an application not because the valuation is right, but because the paying party failed to serve a valid payment notice or pay less notice in time. For the better part of a decade the courts have been mapping the boundaries of that tactic and of its counterweight, the true-value adjudication. The map is now reasonably settled. The casualties are the parties who have not read it.

PT.01

The notified sum rule

5days
The payment notice window

Under section 110A of the Construction Act, a payment notice must be given not later than five days after the payment due date. In its absence, a compliant application for payment can itself become the notified sum.

The machinery is unforgiving by design. The Housing Grants, Construction and Regeneration Act 1996, as amended, requires the notified sum to be paid on or before the final date for payment.¹ A payer intending to pay less must say so in a valid pay less notice, served within the prescribed period and setting out the sum it considers due and the basis on which that sum is calculated.² Serve nothing, or serve something defective, and section 111 converts the payee's application into an enforceable debt. Adjudicators enforce it, and the TCC enforces the adjudicators.

The reported cases turn on small administrative facts: a notice served a day late, a notice that states a figure without the basis of calculation, an application issued outside the contractual window, a due date miscalculated under a bespoke payment schedule. The valuation merits are irrelevant at this stage. That is not a defect in the regime; it is the point of it. Cash flow first, argument afterwards.

PT.02

The Grove counterweight

Authority
S&T (UK) Ltd v Grove Developments Ltd
[2018] EWCA Civ 2448 | Court of Appeal

The employer who misses its notices must pay the notified sum, but may then commence its own adjudication on the true value of the works. The decision dismantled the idea that a missed notice fixes the valuation for good.³

Read the source

Grove restored balance, but on strict terms. The right to a true-value adjudication arises only once the section 111 obligation has been discharged. In M Davenport Builders v Greer, the court refused to let a paying party deploy a true-value decision as a set-off against an unpaid notified sum.⁴ In Bexheat v Essex Services Group, the point was put beyond argument: the immediate payment obligation must be performed before a true-value adjudication on the same cycle can be pursued.⁵

Pay now, argue later is not a slogan. It is the sequencing rule the courts actually enforce.

The margins still generate litigation, notably over when the right to refer a true valuation accrues and what happens to a reference launched prematurely, as in Henry Construction Projects v Alu-Fix.⁶ But the architecture is stable. The notified sum is a debt. The true value is a later question.

PT.03

Losses that were never about valuation

Step back from the authorities and a pattern emerges: very few smash-and-grab defeats involve a genuine disagreement about what the works were worth. They involve paperwork. Payment administration is typically manual, distributed across a commercial team, and invisible until it fails; a payment calendar that quietly diverged from the contract after the works were varied is discovered only when the money has already moved.

Where the machinery breaks
  • 01Due dates miscalculated under amended or bespoke payment schedules
  • 02Payment notices served late, or without the required basis of calculation
  • 03Pay less notices that respond to the wrong application or state a bare figure
  • 04Applications for payment that are themselves invalid: served early, served late, or lacking the substantiation the contract demands
PT.04

Discipline as a system

The Meritus View

At Meritus Via, we treat payment-cycle discipline as an engineering problem. Our deadline engines hold every live contract's payment calendar, from due dates to notice windows to final dates for payment, and track compliance in real time, so a five-day window is never discovered in retrospect. When a dispute crystallises, the notice chronology is already assembled and evidenced.

The same discipline serves the referring party. A smash-and-grab succeeds or fails on the validity of the application and the invalidity of the response. Both are documentary questions, and both reward the party who can put a complete notice record in front of an adjudicator on day one.

The payment regime exists to keep cash moving through the industry, and it does. But it rewards administrative precision over commercial merit, and it will keep transferring money from the disorganised to the organised until notices are treated with the seriousness the statute always intended.

The views expressed in this article are those of the author and are intended for general information only. They do not constitute legal advice and should not be relied upon as such. Specific professional advice should be sought in relation to any particular matter.

Discuss your position

Direct access to a partner. No intermediaries.

Discuss Your Matter
100GB+
Per matter. In hours.